Construction of Flood Mitigation Structure23FE0069

Construction of Flood Control along Bicol River, Brgy. District II, Gainza, Camarines Sur

Construction of Flood Control along Bicol River, Brgy. District II, Gainza, Camarines Sur is a DPWH-tracked public work in GAINZA (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱72,375,000.00. Status: Reported complete (DPWH). Contractor on record: BICOL GOLDROCK CONST CORP. Figures trace to sumbong.

GAINZA (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0023529

₱617,483.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱72,375,000.00

Progress

Reported complete (DPWH)

Start Date

April 5, 2023

Target End

February 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.