Construction of Flood Mitigation Structure23EH0082

Construction of Carmen Flood Control, San Agustin, Romblon

Construction of Carmen Flood Control, San Agustin, Romblon is a DPWH-tracked public work in SAN AGUSTIN (ROMBLON), ROMBLON, Region IV-B. Reported contract value: ₱48,993,645.35. Status: Reported complete (DPWH). Contractor on record: EMQ DESIGN & CONST. Figures trace to sumbong.

SAN AGUSTIN (ROMBLON), ROMBLON, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱48,993,645.35

Progress

Reported complete (DPWH)

Start Date

March 27, 2023

Target End

November 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.